GWA Ugum Reservoir No. 02 Construction

Overview

Construction of a 2.0 MG pre-stressed concrete water reservoir (No. 2) on pile foundation, integrated with existing treatment plant to maintain uninterrupted service.

Detailed Scope

Site clearing/demolition; 2.0 MG tank on pile foundation; control building; major earthwork; piping and tie-ins; protective coatings; flow meters/valves; concrete vaults/retaining walls/headwalls; roadways; site lighting; CCTV; fencing; electrical; I&C; SCADA; testing/commissioning.

Challenges & Solutions

Critical tank build with 147 concrete piles; sequencing to keep adjacent existing tank operational; tight coordination of piping, electrical, and controls to minimize service disruption.

Safety & Compliance

Approved Trenching & Excavation Plan (all excavations); SWPPP; Emergency Preparedness Plan; full documentation to meet stringent safety requirements.

Quality Control

(If you have additional QC items for this project, add here; otherwise omit section.)

Gallery
Project Brief

Location: Inarajan, Guam
Client: Guam Waterworks Authority (GWA)
Current Contract Amount: $23,209,079.49
Award Date: Dec 22, 2023
Estimated Completion: Nov 29, 2026
Status: Ongoing